Closed EoI 2014 for 1st Quarter 2015

Important Information: This call for expressions of interest is closed – recent ones can be found here

Call for expressions of interest in accordance with § 4 para 2 of the German Regulation on Reserve Power Plants (ResKV) for the 1st quarter of 2015 (545 MW)

In accordance with the provisions of the German regulation on reserve power plants (abbr.  Reservekraftwerksverordnung - ResKV) dated 27 June 2013, the German regulatory authority Bundesnetzagentur has examined the requirement for additional reserve power for the network reserve as calculated by the transmission system operators for the first quarter in 2015, and has published the  associated report in accordance with s. 3 para 1 ResKV.

The report by Bundesnetzagentur from 26th September 2014 identifies a direct additional requirement for a total of 545 MW generation capacity for the network reserve. To cover the required generation capacity, the transmission system operators launch a call for expressions of interest in accordance with § 4 ResKV.

We hereby invite interested operators of electricity generation or storage facilities (“plant”) to submit an expression of interest in accordance with § 4 para 2 ResKV to have their plant included in the network reserve from 1st January 2015. To submit expressions of interest, interested operators are required to complete the documents supplied for the purpose and to return them to the responsible transmission system operator, both electronically and in printed form:

Details of the specific prerequisites and requirements for the plants and/or plant operators, including the geographical network region in question and the technical parameters involved, are included in the documents provided.

The deadline for submissions of expressions of interest to have plants included in the network reserve from 1st January 2015 is 15th October 2014. The stamp showing the date of receipt by post shall determine whether expressions of interest have been submitted in good time.

Any contracts will depend on approval by Bundesnetzagentur, especially regarding the selection of plant operators to be contracted and resulting financial obligations upon the responsible transmission system operator. There is no legal entitlement to conclude a contract.

Amprion GmbH reserves the right to change the published information without further announcements.